Behind plan
Supply and construction of two Nasiriyah treatment plants (Sob al-Jazira, design capacity 70,000 m3 per day, and Sob al-Shamiya, 65,000 m3 per day)
Sewage project No. 177 in Dhi Qar.
تجهيز وتنفيذ محطتي معالجة الناصرية (صوب الجزيرة بطاقة تصميمية (70000)م3/يوم +صوب الشامية بطاقة تصميمية (65000)م3/يوم)
Actual progress 82.7% as of 1 Jun 2026
Where the plan says it should be 100% 17.3 points behind
Progress against plan
17.3 points below planned progress
Timeline
2008
2026
- Started
- 30 Oct 2008
- Contract end
- 17 Nov 2026
- Running for
- 17.6 years
- Data as of
- 1 Jun 2026