Behind plan

Study, design, construction, supply, operation and maintenance of stormwater and sewage networks with lift stations and treatment plant for Mahnawiya district, Diwaniyah

Sewage project No. 149 in Al-Qadisiyah (Diwaniyah).

اعداد الدراسة والتصاميم وتنفيذ وتجهيز وتشغيل وصيانة مشروع مجاري شبكات مياه الامطار والثقيلة مع محطات الرفع ومحطة المعالجة لقضاء المهناوية / محافظة الديوانية

Actual progress 10% as of 1 Jun 2026
Where the plan says it should be 39% 29 points behind

Progress against plan

29 points below planned progress

Timeline

Started
22 Aug 2024
Contract end
25 Jan 2027
Running for
1.8 years
Data as of
1 Jun 2026