Behind plan
Ghammas sewage project, phase 1
Sewage project No. 147 in Al-Qadisiyah (Diwaniyah).
مشروع مجاري غماس / م 1
Actual progress 58% as of 1 Jun 2026
Where the plan says it should be 90% 32 points behind
Progress against plan
32 points below planned progress
Timeline
2023
2026
- Started
- 6 Mar 2023
- Contract end
- 10 Aug 2026
- Running for
- 3.2 years
- Data as of
- 1 Jun 2026