Past contract end
Diwaniyah sewage project, phase 2, capacity 100,000 m3 per day (turnkey), with Noor Al-Ufuq added as main partner
Sewage project No. 146 in Al-Qadisiyah (Diwaniyah).
مشروع مجاري الديوانية م2 بطاقة (100000) م3/يوم(تسليم مفتاح) بعد ادخال شركة نور الافق كشريك اساسي
Actual progress 90.8% as of 1 Jun 2026
Where the plan says it should be 100% 9.2 points behind
Progress against plan
Contract ended 14 Jan 2026, 138 days before the data date
Timeline
2011
2026
- Started
- 27 Nov 2011
- Contract end
- 14 Jan 2026
- Running for
- 14.5 years
- Data as of
- 1 Jun 2026