On track

Study, design, construction, supply, operation and maintenance of stormwater and sewage networks with lift stations and treatment plant for Sumer district

Sewage project No. 151 in Al-Qadisiyah (Diwaniyah).

اعداد الدراسة والتصاميم وتنفيذ وتجهيز وتشغيل وصيانة مشروع مجاري شبكات مياه الأمطار والثقيلة مع محطات الرفع ومحطة المعالجة لقضاء سومر

Actual progress 0.5% as of 1 Jun 2026
Where the plan says it should be 3% 2.5 points behind

Progress against plan

Contract ends 23 Oct 2026

Timeline

Started
26 Feb 2025
Contract end
23 Oct 2026
Running for
1.3 years
Data as of
1 Jun 2026