Past contract end

Zghaiton and Al-Shai bridges on the alternative Tikrit to Tuz road

Roads and bridges project No. 266 in Salah al-Din.

انشاء جسري زغيتون والشاي على طريق تكريت الطوز البديل

When will the Zghaiton and Al-Shai bridges on the alternative Tikrit to Tuz road be finished? The contract end date was 23 Aug 2021. As of 1 Jun 2026 the Ministry of Construction reported it 23% complete, against 23% planned. The published data gives no revised completion date.

Actual progress 23% as of 1 Jun 2026
Where the plan says it should be 23%

Progress against plan

Contract ended 23 Aug 2021, 1,743 days before the data date

Timeline

Started
10 Mar 2013
Contract end
23 Aug 2021
Running for
13.2 years
Data as of
1 Jun 2026