Tikrit concrete bridge (north Tikrit bridge), approaches, phase two
Roads and bridges project No. 264 in Salah al-Din.
مشروع انشاء جسر تكريت الكونكريتي(جسر شمال تكريت) المقتربات المرحلة الثانية
When will the Tikrit concrete bridge (north Tikrit bridge), approaches, phase two be finished? The contract end date was 10 Feb 2026. As of 1 Jun 2026 the Ministry of Construction reported it 38.6% complete, against 85.7% planned. The published data gives no revised completion date.
Actual progress 38.6% as of 1 Jun 2026
Where the plan says it should be 85.7% 47.1 points behind
Progress against plan
Contract ended 10 Feb 2026, 111 days before the data date
Timeline
2023
2026
- Started
- 23 Mar 2023
- Contract end
- 10 Feb 2026
- Running for
- 3.2 years
- Data as of
- 1 Jun 2026