On track

Balad intersection overpasses on the Baghdad to Mosul road

Roads and bridges project No. 265 in Salah al-Din.

انشاء مجسرات تقاطع بلد على طريق بغداد - موصل

When will the Balad intersection overpasses on the Baghdad to Mosul road be finished? The contract end date is 30 Jun 2026. As of 1 Jun 2026 the Ministry of Construction reported it 85% complete, against 87.7% planned. The published data gives no revised completion date.

Actual progress 85% as of 1 Jun 2026
Where the plan says it should be 87.7% 2.7 points behind

Progress against plan

Contract ends 30 Jun 2026

Timeline

Started
21 Apr 2025
Contract end
30 Jun 2026
Running for
1.1 years
Data as of
1 Jun 2026