Past contract end

Maintenance of the Kirkuk to Sulaymaniyah road

Roads and bridges project No. 261 in Kirkuk.

صيانة طريق كركوك- سليمانية

Actual progress 41.3% as of 1 Jun 2026
Where the plan says it should be 58.2% 16.9 points behind

Progress against plan

Contract ended 23 Mar 2026, 70 days before the data date

Timeline

Started
17 Feb 2025
Contract end
23 Mar 2026
Running for
1.3 years
Data as of
1 Jun 2026