Past contract end
Maintenance of the Kirkuk to Sulaymaniyah road
Roads and bridges project No. 261 in Kirkuk.
صيانة طريق كركوك- سليمانية
Actual progress 41.3% as of 1 Jun 2026
Where the plan says it should be 58.2% 16.9 points behind
Progress against plan
Contract ended 23 Mar 2026, 70 days before the data date
Timeline
2025
2026
- Started
- 17 Feb 2025
- Contract end
- 23 Mar 2026
- Running for
- 1.3 years
- Data as of
- 1 Jun 2026