Past contract end
Rehabilitation and maintenance of the Baghdad to Kirkuk road, 162 km
Roads and bridges project No. 262 in Kirkuk.
مشروع تأهيل وصيانة طريق بغداد - كركوك بطول 162 كم
Actual progress 90.6% as of 1 Jun 2026
Where the plan says it should be 100% 9.5 points behind
Progress against plan
Contract ended 2 Nov 2024, 576 days before the data date
Timeline
2022
Contract end
2026
- Started
- 15 Jan 2022
- Contract end
- 2 Nov 2024
- Running for
- 4.4 years
- Data as of
- 1 Jun 2026