Past contract end

Rehabilitation and development of the single Dutch bridge

Roads and bridges project No. 321 in Dhi Qar.

تاهيل وتطوير الجسر الهولندي المفرد

When will the Rehabilitation and development of the single Dutch bridge be finished? The contract end date was 10 May 2026. As of 1 Jun 2026 the Ministry of Construction reported it 69.9% complete, against 79.4% planned. The published data gives no revised completion date.

Actual progress 69.9% as of 1 Jun 2026
Where the plan says it should be 79.4% 9.5 points behind

Progress against plan

Contract ended 10 May 2026, 22 days before the data date

Timeline

Started
30 Jul 2024
Contract end
10 May 2026
Running for
1.8 years
Data as of
1 Jun 2026