Past contract end

Remaining works on the north Nasiriyah bridge and approaches (phase one, river bridge), Dhi Qar (at the expense of the defaulting contractor)

Roads and bridges project No. 320 in Dhi Qar.

الاعمال المتبقية لمشروع جسر شمال الناصرية ومقترباته/ (المرحلة الاولى) الجسر النهري في محافظة ذي قار(على حساب المقاول النأكل)

When will the Remaining works on the north Nasiriyah bridge and approaches (phase one, river bridge), Dhi Qar (at the expense of the defaulting contractor) be finished? The contract end date was 3 May 2026. As of 1 Jun 2026 the Ministry of Construction reported it 94.3% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 94.3% as of 1 Jun 2026
Where the plan says it should be 100% 5.7 points behind

Progress against plan

Contract ended 3 May 2026, 29 days before the data date

Timeline

Started
13 Oct 2019
Contract end
3 May 2026
Running for
6.6 years
Data as of
1 Jun 2026