Past contract end

Second carriageway at Tarmiya, Baghdad to Mosul entrance, 13 km, Baghdad

Roads and bridges project No. 340 across several provinces.

انشاء ممر ثاني طارمية مدخل بغداد موصل بطول 13 كم / بغداد

Actual progress 95.3% as of 1 Jun 2026
Where the plan says it should be 100% 4.7 points behind

Progress against plan

Contract ended 12 Jun 2024, 719 days before the data date

Timeline

Started
9 Oct 2012
Contract end
12 Jun 2024
Running for
13.6 years
Data as of
1 Jun 2026