Behind plan

Residential complex in Diwaniyah, Afak

Housing project No. 87 in Al-Qadisiyah (Diwaniyah).

انشاء مجمع سكني في محافظة الديوانية/ عفك

Actual progress 33.7% as of 1 Jun 2026
Where the plan says it should be 51.7% 18 points behind

Progress against plan

18 points below planned progress

Timeline

Started
13 Feb 2014
Running for
12.3 years
Data as of
1 Jun 2026