Past contract end

Residential complex in Diwaniyah, Jibsa and Shamiya

Housing project No. 88 in Al-Qadisiyah (Diwaniyah).

انشاء مجمع سكني في محافظة الديوانية / الجبسة والشامية

Actual progress 76.1% as of 1 Jun 2026
Where the plan says it should be 85% 8.9 points behind

Progress against plan

Contract ended 11 Jul 2025, 325 days before the data date

Timeline

Started
3 Jul 2023
Contract end
11 Jul 2025
Running for
2.9 years
Data as of
1 Jun 2026