Past contract end
Residential complex in Diwaniyah, Jibsa and Shamiya
Housing project No. 88 in Al-Qadisiyah (Diwaniyah).
انشاء مجمع سكني في محافظة الديوانية / الجبسة والشامية
Actual progress 76.1% as of 1 Jun 2026
Where the plan says it should be 85% 8.9 points behind
Progress against plan
Contract ended 11 Jul 2025, 325 days before the data date
Timeline
2023
Contract end
2026
- Started
- 3 Jul 2023
- Contract end
- 11 Jul 2025
- Running for
- 2.9 years
- Data as of
- 1 Jun 2026