On track
Third Kufa bridge (Imam Ali bridge)
Roads and bridges project No. 301 in Najaf.
جسر الكوفة الثالث (جسر الامام علي (ع))
When will the Third Kufa bridge (Imam Ali bridge) be finished? The contract end date is 5 Sept 2026. As of 1 Jun 2026 the Ministry of Construction reported it 87.5% complete, against 88.5% planned. The published data gives no revised completion date.
Actual progress 87.5% as of 1 Jun 2026
Where the plan says it should be 88.5% 1 points behind
Progress against plan
Contract ends 5 Sept 2026
Timeline
2024
2026
- Started
- 28 Feb 2024
- Contract end
- 5 Sept 2026
- Running for
- 2.3 years
- Data as of
- 1 Jun 2026