On track

Fifth Kufa bridge

Roads and bridges project No. 304 in Najaf.

مشروع انشاء جسر الكوفة الخامس

When will the Fifth Kufa bridge be finished? The contract end date is 22 Jun 2028. As of 1 Jun 2026 the Ministry of Construction reported it 0.1% complete, against 0.1% planned. The published data gives no revised completion date.

Actual progress 0.1% as of 1 Jun 2026
Where the plan says it should be 0.1% 0.1 points behind

Progress against plan

Contract ends 22 Jun 2028

Timeline

Started
4 Jan 2026
Contract end
22 Jun 2028
Running for
0.4 years
Data as of
1 Jun 2026