On track

Ramadi water project, capacity 10,000 m3 per hour

Water project No. 224 in Anbar.

مشروع ماء الرمادي بطاقة 10000م3/سا

Actual progress 2% as of 1 Jun 2026
Where the plan says it should be 2.8% 0.8 points behind

Progress against plan

Contract ends 2 Dec 2028

Timeline

Started
18 Dec 2025
Contract end
2 Dec 2028
Running for
0.5 years
Data as of
1 Jun 2026