On track
East Husaiba water project in Anbar (2024)
Water project No. 220 in Anbar.
انشاء مشروع ماء حصيبة الشرقية في محافظة الانبار /2024
Actual progress 53.2% as of 1 Jun 2026
Where the plan says it should be 33%
Progress against plan
Contract ends 11 Sept 2027
Timeline
2024
2027
- Started
- 25 Nov 2024
- Contract end
- 11 Sept 2027
- Running for
- 1.5 years
- Data as of
- 1 Jun 2026