Drinking water projects in Anbar
The Ministry of Construction lists 5 drinking water projects in Anbar: 1 past contract end, 1 behind plan, 3 on track, as of 1 Jun 2026.
On track3
Behind plan1
Past contract end1
Baghdadi water project in Anbar (2008) Contract ended 3 Apr 2024, 789 days before the data date Past contract end Kartan water project, capacity 1,000 m3 per hour 33.5 points below planned progress Behind plan East Husaiba water project in Anbar (2024) Contract ends 11 Sept 2027 On track Fallujah water project in Anbar (2004) Contract ends 2 Aug 2026 On track Ramadi water project, capacity 10,000 m3 per hour Contract ends 2 Dec 2028 On track
Source: Ministry of Construction, status as of 1 Jun 2026Details