Behind plan
Kartan water project, capacity 1,000 m3 per hour
Water project No. 223 in Anbar.
مشروع ماء كرطان بطاقة 1000م3/ساعة
Actual progress 4% as of 1 Jun 2026
Where the plan says it should be 37.5% 33.5 points behind
Progress against plan
33.5 points below planned progress
Timeline
2025
2027
- Started
- 2 Aug 2025
- Contract end
- 2 Aug 2027
- Running for
- 0.8 years
- Data as of
- 1 Jun 2026