On track
Infrastructure rehabilitation and development, phase two, Hay district
Sewage project No. 144 in Wasit.
تأهيل وتطوير البنى التحتية المرحلة الثانية في قضاء الحي
Actual progress 63% as of 1 Jun 2026
Where the plan says it should be 59%
Progress against plan
Contract ends 27 Feb 2027
Timeline
2025
2027
- Started
- 23 Feb 2025
- Contract end
- 27 Feb 2027
- Running for
- 1.3 years
- Data as of
- 1 Jun 2026