Design review, supply, construction, operation and maintenance of the Bartella sewage network and plant, Nineveh (design capacity 4,942 m3 per day)
Sewage project No. 110 in Nineveh.
تدقيق تصاميم وتجهيز وتنفيذ وتشغيل وصيانة شبكة ومحطة مجارى برطلة /نينوى بطاقة تصميمية (4942)م3/يوم
Actual progress 94% as of 1 Jun 2026
Where the plan says it should be 100% 6 points behind
Progress against plan
Contract ended 3 Jan 2026, 149 days before the data date
Timeline
2012
2026
- Started
- 20 Jun 2012
- Contract end
- 3 Jan 2026
- Running for
- 13.9 years
- Data as of
- 1 Jun 2026