Past contract end

Supply and construction of stormwater trunk lines with lift stations SL46 and SL47, left bank of Mosul

Sewage project No. 112 in Nineveh.

تجهيز وتنفيذ الخطوط الناقلة المطرية مع محطتي الرفع (SL46وSL47)الجانب الأيسر /الموصل

Actual progress 89% as of 1 Jun 2026
Where the plan says it should be 100% 11 points behind

Progress against plan

Contract ended 9 Jan 2026, 143 days before the data date

Timeline

Started
2 Dec 2012
Contract end
9 Jan 2026
Running for
13.5 years
Data as of
1 Jun 2026