Past contract end
Supply and construction of sewage trunk lines with four lift stations, left bank of Mosul, phase four
Sewage project No. 113 in Nineveh.
تجهيز وتنفيذ الخطوط الناقلة للمجارى الثقيلة مع اربع محطات رفع لمدينة الموصل /الجانب الايسر/المرحلة الرابعة
Actual progress 63% as of 1 Jun 2026
Where the plan says it should be 87.2% 24.2 points behind
Progress against plan
Contract ended 3 Feb 2025, 483 days before the data date
Timeline
2013
2026
- Started
- 9 Jan 2013
- Contract end
- 3 Feb 2025
- Running for
- 13.4 years
- Data as of
- 1 Jun 2026