Past contract end

Supply and construction of sewage trunk lines with four lift stations, left bank of Mosul, phase four

Sewage project No. 113 in Nineveh.

تجهيز وتنفيذ الخطوط الناقلة للمجارى الثقيلة مع اربع محطات رفع لمدينة الموصل /الجانب الايسر/المرحلة الرابعة

Actual progress 63% as of 1 Jun 2026
Where the plan says it should be 87.2% 24.2 points behind

Progress against plan

Contract ended 3 Feb 2025, 483 days before the data date

Timeline

Started
9 Jan 2013
Contract end
3 Feb 2025
Running for
13.4 years
Data as of
1 Jun 2026