Past contract end
Supply and construction of the treatment plant for the right bank of Mosul, phase 1
Sewage project No. 114 in Nineveh.
تجهيز وتنفيذ محطة معالجة الجانب الايمن لمدينة الموصل / م1
Actual progress 62% as of 1 Jun 2026
Where the plan says it should be 100% 38 points behind
Progress against plan
Contract ended 14 Jul 2024, 687 days before the data date
Timeline
2013
2026
- Started
- 3 Sept 2013
- Contract end
- 14 Jul 2024
- Running for
- 12.7 years
- Data as of
- 1 Jun 2026