Past contract end

Bridges of expressway section T/6, km 0 to km 144.8

Roads and bridges project No. 333 across several provinces.

جسور مشروع المرور السريع ط/6 كم ـ(000+0) - ـ(819+144)

When will the Bridges of expressway section T/6, km 0 to km 144.8 be finished? The contract end date was 31 Aug 2023. As of 1 Jun 2026 the Ministry of Construction reported it 99.5% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 99.5% as of 1 Jun 2026
Where the plan says it should be 100% 0.5 points behind

Progress against plan

Contract ended 31 Aug 2023, 1,005 days before the data date

Timeline

Started
10 Nov 2011
Contract end
31 Aug 2023
Running for
14.6 years
Data as of
1 Jun 2026