Behind plan
Phase three of the shrine of Martyr Mohammed Baqir al-Sadr
Buildings project No. 17 in Najaf.
تنفيذ المرحلة الثالثة لمرقد الشهيد محمد باقر الصدر (قدس سره)
Actual progress 45.2% as of 1 Jun 2026
Where the plan says it should be 55.4% 10.3 points behind
Progress against plan
10.3 points below planned progress
Timeline
2024
2027
- Started
- 12 Feb 2024
- Contract end
- 20 Sept 2027
- Running for
- 2.3 years
- Data as of
- 1 Jun 2026