Behind plan

Phase three of the shrine of Martyr Mohammed Baqir al-Sadr

Buildings project No. 17 in Najaf.

تنفيذ المرحلة الثالثة لمرقد الشهيد محمد باقر الصدر (قدس سره)

Actual progress 45.2% as of 1 Jun 2026
Where the plan says it should be 55.4% 10.3 points behind

Progress against plan

10.3 points below planned progress

Timeline

Started
12 Feb 2024
Contract end
20 Sept 2027
Running for
2.3 years
Data as of
1 Jun 2026