On track
Residential complex in Basra, Qibla
Housing project No. 108 in Basra.
انشاء مجمع سكني في محافظة البصرة/ القبلة
Actual progress 56.9% as of 1 Jun 2026
Where the plan says it should be 65% 8.1 points behind
Progress against plan
No contract end date given
Timeline
- Started
- 12 Oct 2011
- Running for
- 14.6 years
- Data as of
- 1 Jun 2026