Past contract end
Residential complex in Basra, Shatt al-Arab 1
Housing project No. 104 in Basra.
انشاء مجمع سكني في محافظة البصرة/شط العرب1
Actual progress 67.3% as of 1 Jun 2026
Where the plan says it should be 83% 15.7 points behind
Progress against plan
Contract ended 20 Dec 2021, 1,624 days before the data date
Timeline
2019
Contract end
2026
- Started
- 27 Aug 2019
- Contract end
- 20 Dec 2021
- Running for
- 6.8 years
- Data as of
- 1 Jun 2026