Behind plan
Residential complex in Basra, Shatt al-Arab 2
Housing project No. 107 in Basra.
انشاء مجمع سكني في محافظة البصرة/ شط العرب 2
Actual progress 50.1% as of 1 Jun 2026
Where the plan says it should be 98.2% 48.2 points behind
Progress against plan
48.2 points below planned progress
Timeline
2023
2026
- Started
- 8 Nov 2023
- Contract end
- 1 Jun 2026
- Running for
- 2.6 years
- Data as of
- 1 Jun 2026