Behind plan

Reconstruction of the Ministry of Planning building complex (C, D, E, F, H, I, J, K, L)

Buildings project No. 8 in Baghdad.

أعادة أعمار مجمع وزارة التخطيط للأبنية (C.D.E.F.H.I.J.K.L)

Actual progress 67.2% as of 1 Jun 2026
Where the plan says it should be 77.9% 10.7 points behind

Progress against plan

10.7 points below planned progress

Timeline

Started
9 Oct 2025
Contract end
21 Jul 2026
Running for
0.6 years
Data as of
1 Jun 2026