Behind plan
Reconstruction of the Ministry of Planning building complex (C, D, E, F, H, I, J, K, L)
Buildings project No. 8 in Baghdad.
أعادة أعمار مجمع وزارة التخطيط للأبنية (C.D.E.F.H.I.J.K.L)
Actual progress 67.2% as of 1 Jun 2026
Where the plan says it should be 77.9% 10.7 points behind
Progress against plan
10.7 points below planned progress
Timeline
2025
2026
- Started
- 9 Oct 2025
- Contract end
- 21 Jul 2026
- Running for
- 0.6 years
- Data as of
- 1 Jun 2026