Past contract end
Widening of the embankment from the Saqlawiya concrete bridge to expressway intersection 51, 14.6 km, with a 2 km service road for low cost housing and a 1.7 km road from the Japanese bridge to the Nazim bridge
Roads and bridges project No. 274 in Anbar.
مشروع توسيع السدة من جسر الصقلاوية الكونكريتي الى طريق المرور السريع تقاطع (51) بطول 14.6 كم مع انشاء طريق خدمي لدور واطئة الكلفة بطول 2 كم وانشاء طريق من الجسر الياباني لجسر الناظم بطول 1.7 كم
When will the Widening of the embankment from the Saqlawiya concrete bridge to expressway intersection 51, 14.6 km, with a 2 km service road for low cost housing and a 1.7 km road from the Japanese bridge to the Nazim bridge be finished? The contract end date was 10 May 2026. As of 1 Jun 2026 the Ministry of Construction reported it 9.9% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 9.9% as of 1 Jun 2026
Where the plan says it should be 100% 90.1 points behind
Progress against plan
Contract ended 10 May 2026, 22 days before the data date
Timeline
2025
2026
- Started
- 22 Jul 2025
- Contract end
- 10 May 2026
- Running for
- 0.9 years
- Data as of
- 1 Jun 2026