Past contract end
Rehabilitation of the Ramadi to Rahaliya road, starting at the Kahawi area
Roads and bridges project No. 275 in Anbar.
تأهيل طريق رمادي /رحالية باعتبار (0+000) منطقة الكهاوي
Actual progress 88.2% as of 1 Jun 2026
Where the plan says it should be 100% 11.9 points behind
Progress against plan
Contract ended 25 Aug 2025, 280 days before the data date
Timeline
2025
Contract end
2026
- Started
- 26 Feb 2025
- Contract end
- 25 Aug 2025
- Running for
- 1.3 years
- Data as of
- 1 Jun 2026