Past contract end

Completion works for the Kirkuk building

Municipal services project No. 192 in Kirkuk.

مشروع الاعمال التكميلية لبناية كركوك

Actual progress 47% as of 1 Jun 2026
Where the plan says it should be 100% 53 points behind

Progress against plan

Contract ended 2 Feb 2026, 119 days before the data date

Timeline

Started
28 May 2025
Contract end
2 Feb 2026
Running for
1 year
Data as of
1 Jun 2026