On track
Supply and construction of the treatment plant for the right bank of Mosul, phase 2
Sewage project No. 115 in Nineveh.
تجهيز وتنفيذ محطة معالجة الجانب الايمن لمدينة الموصل/ م2
Actual progress 80.3% as of 1 Jun 2026
Where the plan says it should be 83.5% 3.2 points behind
Progress against plan
Contract ends 12 Jan 2027
Timeline
2013
2027
- Started
- 21 Nov 2013
- Contract end
- 12 Jan 2027
- Running for
- 12.5 years
- Data as of
- 1 Jun 2026