On track

Supply and construction of the treatment plant for the right bank of Mosul, phase 2

Sewage project No. 115 in Nineveh.

تجهيز وتنفيذ محطة معالجة الجانب الايمن لمدينة الموصل/ م2

Actual progress 80.3% as of 1 Jun 2026
Where the plan says it should be 83.5% 3.2 points behind

Progress against plan

Contract ends 12 Jan 2027

Timeline

Started
21 Nov 2013
Contract end
12 Jan 2027
Running for
12.5 years
Data as of
1 Jun 2026