Past contract end

Qal'at Salih concrete bridge and approaches

Roads and bridges project No. 316 in Maysan.

انشاء جسر قلعة صالح الكونكريتي ومقترباتة

When will the Qal'at Salih concrete bridge and approaches be finished? The contract end date was 22 Apr 2026. As of 1 Jun 2026 the Ministry of Construction reported it 10% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 10% as of 1 Jun 2026
Where the plan says it should be 100% 90 points behind

Progress against plan

Contract ended 22 Apr 2026, 40 days before the data date

Timeline

Started
27 Jun 2025
Contract end
22 Apr 2026
Running for
0.9 years
Data as of
1 Jun 2026