Past contract end
Dur al-Naft concrete bridge and approaches
Roads and bridges project No. 314 in Maysan.
انشاء جسر دور النفط الكونكريتي ومقترباته
When will the Dur al-Naft concrete bridge and approaches be finished? The contract end date was 22 Apr 2026. As of 1 Jun 2026 the Ministry of Construction reported it 9% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 9% as of 1 Jun 2026
Where the plan says it should be 100% 91 points behind
Progress against plan
Contract ended 22 Apr 2026, 40 days before the data date
Timeline
2025
2026
- Started
- 27 Jun 2025
- Contract end
- 22 Apr 2026
- Running for
- 0.9 years
- Data as of
- 1 Jun 2026