Past contract end
Supply and construction of the stormwater drainage trunk line for the southern area, Fallujah
Sewage project No. 134 in Anbar.
مشروع تجهيز وتنفيذ الخط الناقل لتصريف مياه الامطار للمنطقة الجنوبية/الفلوجة
Actual progress 79% as of 1 Jun 2026
Where the plan says it should be 100% 21 points behind
Progress against plan
Contract ended 22 Mar 2026, 71 days before the data date
Timeline
2025
Contract end
2026
- Started
- 7 Apr 2025
- Contract end
- 22 Mar 2026
- Running for
- 1.1 years
- Data as of
- 1 Jun 2026