Past contract end

Supply and construction of the stormwater drainage trunk line for the southern area, Fallujah

Sewage project No. 134 in Anbar.

مشروع تجهيز وتنفيذ الخط الناقل لتصريف مياه الامطار للمنطقة الجنوبية/الفلوجة

Actual progress 79% as of 1 Jun 2026
Where the plan says it should be 100% 21 points behind

Progress against plan

Contract ended 22 Mar 2026, 71 days before the data date

Timeline

Started
7 Apr 2025
Contract end
22 Mar 2026
Running for
1.1 years
Data as of
1 Jun 2026