On track
Sewage and stormwater networks for Ana subdistrict, Anbar (infrastructure)
Sewage project No. 135 in Anbar.
تنفيذ مشروع مجاري الصرف الصحي وشبكات مجاري مياه امطار ناحية عنه/ محافظة الانبار (البنى التحتية)
Actual progress 29.5% as of 1 Jun 2026
Where the plan says it should be 29.4%
Progress against plan
Contract ends 8 Jun 2028
Timeline
2025
2028
- Started
- 2 Jun 2025
- Contract end
- 8 Jun 2028
- Running for
- 1 year
- Data as of
- 1 Jun 2026