Completed
Second carriageway of the Jalawla to Qara Tapa road, 36.1 km
Roads and bridges project No. 348 in Diyala.
انشاء الممر الثاني لطريق جلولاء - قرة تبة بطول 36.1 كم
Actual progress 100% as of 1 Jun 2026
Where the plan says it should be 100%
Progress against plan
Timeline
2023
Contract end
2026
- Started
- 6 Jun 2023
- Contract end
- 12 Feb 2025
- Running for
- 3 years
- Data as of
- 1 Jun 2026