Past contract end

Additional floor for the Engineering Reconstruction Directorate building

Buildings project No. 7 in Baghdad.

أضافة طابق ملحق الى بناية دائرة الأعمار الهندسي

Actual progress 58% as of 1 Jun 2026
Where the plan says it should be 69% 11 points behind

Progress against plan

Contract ended 1 May 2026, 31 days before the data date

Timeline

Started
10 Jul 2025
Contract end
1 May 2026
Running for
0.9 years
Data as of
1 Jun 2026