On track
Sewage networks project, right bank of Mosul
Sewage project No. 118 in Nineveh.
مشروع شبكات المجاري / الجانب الايمن / مدينة الموصل
Actual progress 66.2% as of 1 Jun 2026
Where the plan says it should be 68.2% 2 points behind
Progress against plan
Contract ends 5 Nov 2026
Timeline
2022
2026
- Started
- 27 Oct 2022
- Contract end
- 5 Nov 2026
- Running for
- 3.6 years
- Data as of
- 1 Jun 2026