On track
Qara Tapa water project, capacity 2,000 m3 per hour
Water project No. 216 in Diyala.
مشروع ماء قره تبه بطاقة 2000م3/ساعة
Actual progress 3.8% as of 1 Jun 2026
Where the plan says it should be 7% 3.3 points behind
Progress against plan
Contract ends 13 Jul 2028
Timeline
2025
2028
- Started
- 29 Jul 2025
- Contract end
- 13 Jul 2028
- Running for
- 0.8 years
- Data as of
- 1 Jun 2026