Drinking water projects in Diyala
The Ministry of Construction lists 6 drinking water projects in Diyala: 2 past contract end, 1 behind plan, 3 on track, as of 1 Jun 2026.
On track3
Behind plan1
Past contract end2
Al-Salam and Al-Sarajiq water project in Mansuriya Contract ended 11 Apr 2023, 1,147 days before the data date Past contract end Jadidat al-Shatt water project in Diyala (2012) Contract ended 24 Mar 2026, 69 days before the data date Past contract end Khan Bani Saad water project in Diyala (2004) 43.6 points below planned progress Behind plan West Baquba water project, capacity 6,000 m3 per hour Contract ends 7 Jan 2028 On track Qara Tapa water project, capacity 2,000 m3 per hour Contract ends 13 Jul 2028 On track Jalawla water project, capacity 2,000 m3 per hour Contract ends 25 Jun 2028 On track
Source: Ministry of Construction, status as of 1 Jun 2026Details