Behind plan
Design and construction of the Hurriya intersection, Karrada Kharij, including the Hasanain tunnel
Roads and bridges project No. 288 in Baghdad.
تصميم وتنفيذ تقاطع الحرية / كرادة خارج بضمنها نفق الحسنين.
When will the Design and construction of the Hurriya intersection, Karrada Kharij, including the Hasanain tunnel be finished? The contract end date is 13 Jul 2026. As of 1 Jun 2026 the Ministry of Construction reported it 4% complete, against 86% planned. The published data gives no revised completion date.
Actual progress 4% as of 1 Jun 2026
Where the plan says it should be 86% 82 points behind
Progress against plan
82 points below planned progress
Timeline
2025
2026
- Started
- 15 May 2025
- Contract end
- 13 Jul 2026
- Running for
- 1 year
- Data as of
- 1 Jun 2026