Behind plan

Design and construction of the Hurriya intersection, Karrada Kharij, including the Hasanain tunnel

Roads and bridges project No. 288 in Baghdad.

تصميم وتنفيذ تقاطع الحرية / كرادة خارج بضمنها نفق الحسنين.

When will the Design and construction of the Hurriya intersection, Karrada Kharij, including the Hasanain tunnel be finished? The contract end date is 13 Jul 2026. As of 1 Jun 2026 the Ministry of Construction reported it 4% complete, against 86% planned. The published data gives no revised completion date.

Actual progress 4% as of 1 Jun 2026
Where the plan says it should be 86% 82 points behind

Progress against plan

82 points below planned progress

Timeline

Started
15 May 2025
Contract end
13 Jul 2026
Running for
1 year
Data as of
1 Jun 2026