Past contract end

Rehabilitation of the Jumaima border crossing

Roads and bridges project No. 326 in Muthanna.

تأهيل منفذ جميمة الحدودي

Actual progress 2.5% as of 1 Jun 2026
Where the plan says it should be 0.4%

Progress against plan

Contract ended 21 Aug 2025, 284 days before the data date

Timeline

Started
29 Apr 2025
Contract end
21 Aug 2025
Running for
1.1 years
Data as of
1 Jun 2026