Past contract end
Rehabilitation of the Jumaima border crossing
Roads and bridges project No. 326 in Muthanna.
تأهيل منفذ جميمة الحدودي
Actual progress 2.5% as of 1 Jun 2026
Where the plan says it should be 0.4%
Progress against plan
Contract ended 21 Aug 2025, 284 days before the data date
Timeline
2025
Contract end
2026
- Started
- 29 Apr 2025
- Contract end
- 21 Aug 2025
- Running for
- 1.1 years
- Data as of
- 1 Jun 2026