Past contract end
Taza water project in Kirkuk (2011)
Water project No. 210 in Kirkuk.
مشروع ماء تازة في محافظة كركوك /2011
Actual progress 96.7% as of 1 Jun 2026
Where the plan says it should be 100% 3.4 points behind
Progress against plan
Contract ended 28 Jun 2025, 338 days before the data date
Timeline
2012
2026
- Started
- 29 Aug 2012
- Contract end
- 28 Jun 2025
- Running for
- 13.8 years
- Data as of
- 1 Jun 2026