Behind plan
National water and sanitation master plan for the cities, districts and subdistricts of Kirkuk
Water project No. 209 in Kirkuk.
اعداد الخطة الوطنية الرئيسية للماء والصرف الصحي master plan لمدن واقضيةونواحي محافظة كركوك
Actual progress 50% as of 1 Jun 2026
Where the plan says it should be 73% 23 points behind
Progress against plan
23 points below planned progress
Timeline
2025
2026
- Started
- 16 Apr 2025
- Contract end
- 7 Oct 2026
- Running for
- 1.1 years
- Data as of
- 1 Jun 2026