Past contract end

Widening of the Kifl to Najaf road, 10.325 km

Roads and bridges project No. 291 in Babil.

تعريض طريق كفل-نجف بطول 10,325كم

Actual progress 64.2% as of 1 Jun 2026
Where the plan says it should be 100% 35.8 points behind

Progress against plan

Contract ended 14 Jan 2026, 138 days before the data date

Timeline

Started
5 Jan 2025
Contract end
14 Jan 2026
Running for
1.4 years
Data as of
1 Jun 2026